How to Do Many Projects with Few People (Part 1)

October 7, 2008 by JurgenAppelo

ComplexdiagramGiven the problem (most managers call it a 'challenge') of running many dozens of projects concurrently, with just a small number of people, I've been asked a few times how we organize projects and resources in our company. Well, there's a lot to tell about this subject, and my attention span (as a manager) is rather short. So I'll spread that information over several posts.

Many of our customers have simple, small requests: requirements that take just a couple of days or weeks to fulfill. This means that the organizational complexity (some employees call it 'chaos') is vastly different from other companies, where they have teams of many employees working on just one project, often for many months at a time. But I am sure that lots of people face similar problems (or challenges if you prefer) as we do, working on numerous small projects. So let me tell you what we did...

We have many multi-functional teams, where each team is between 4 and 10 people, depending on the types of projects that they do. We firmly believe that everyone who's working on the same projects should be seated together. This vastly improves the project-level communication, and it enables employees to better understand each other's work. For example: there's no point in seating all project managers together, as they are all managing different projects. Their only communication would be about the latest soccer matches, and the new receptionist.

In the case of our software development teams, each team has a number of software developers, one front-end developer, one project manager, one team manager, and (soon) one tester. Our project managers perform the 'ScrumMaster' role, but they also concern themselves with resource planning of their team members across the different (sometimes conflicting) projects in their teams, and any interdependencies among the projects. Their primary concern is that the time they have allocated to projects is, indeed, being spent on those projects. They can often be seen (or heard) scolding people who are trying to steal time from their teams, with questions like "Can you help me with this little problem?" or "Can you call this customer? It shouldn't take more than half an hour." But, given the reduction in red faces and scents of burning hair, this seems to happen less and less often these days.

to be continued...

Comments

We had quite similar problem

October 7, 2008 by pbielicki, 13 weeks 4 hours ago
Comment id: 1892

We had quite similar problem with stealing time and I wrote about it on my private blog: http://java2jee.blogspot.com/2007/01/microiterations-definition.html It was some time before I knew Scrum and our team became extremely agile and efficient (and to be honest this post was the beginning of our agile way :)

One question to your post. You wrote that project manager is the "Scrum Master". What is the role of the team manager, then?

Cheers!
Przemek

Post new comment

The content of this field is kept private and will not be shown publicly.
  • Allowed HTML tags: <a> <b> <i> <em> <strong> <cite> <code> <ul> <ol> <li> <dl> <dt> <dd> <img> <br> <blockquote>
  • Lines and paragraphs break automatically.
  • Web page addresses and e-mail addresses turn into links automatically.
  • You can enable syntax highlighting of source code with the following tags: <code>, <blockcode>. Beside the tag style "<foo>" it is also possible to use "[foo]".

More information about formatting options

CAPTCHA
This question is for testing whether you are a human visitor and to prevent automated spam submissions.

Best of AgileSoftwareDevelopment.com